Update on March 23, 2014

Post date: Mar 24, 2014 5:18:33 AM

1. We prepared almost the whole package ready for pre-application (containing the project description document, site plan, proposed reclamation modification plans, grading rough plans etc) to the Santa Clara county. The docs are given to the county planner and she is co-ordinating with their staff to do the pre-screening tests.

2. Around April 8th, we are meeting the County departments to find out information about what other documents we need to submit for pre-application.

3. Half work has been completed to setup the project office space in the Vaikuntha Hill.